View Single Post
  #9  
Old August 10th 06, 02:43 PM posted to rec.aviation.piloting
Larry Dighera
external usenet poster
 
Posts: 3,953
Default Experiences with the new LockMart FSS?



http://www.aopa.org/whatsnew/newsite...0515audit.html
Inspector general to audit FAA-Lockheed Martin flight service contract
To ensure that general aviation pilots are being served properly, the
Transportation Department's inspector general will be auditing the
contract awarded by the FAA last year to have Lockheed Martin Corp.
take over flight service station (FSS) functions. The contract is one
of the largest nondefense-related outsourcing efforts in the federal
government.

The inspector general's office pointed out in a May 8 memo that it
will be assessing whether the FAA has implemented effective plans and
controls to transition FSS to contract operations and that operational
needs of users continue to be met. The audit is planned to begin
sometime this month. AOPA staff has already talked to officials from
the inspector general's office to make sure they understand pilots'
concerns and experiences with FSS operations. In the course of those
conversations, AOPA has offered to survey its members — Lockheed's FSS
customers — and report back to the inspector general's office in order
to help them determine how well Lockheed is performing.

"The FAA and Lockheed Martin must remain accountable to the users,"
said AOPA President Phil Boyer. "This early look at the program and
the associated plans for changes is important to ensure pilots' needs
are met, which is why AOPA is working closely with the inspector
general of the Department of Transportation."

Lockheed Martin's flight services system is called "Flight Services
21" (FS21) and will be a fully integrated nationwide network that
gives all flight service specialists and pilots access to flight plan
information from a single, common database. AOPA had pushed hard for
specific performance guarantees to improve safety and convenience for
GA pilots.

The FAA has limited experience with outsourcing, and the unusually
large contract deals with important safety issues. Under federal law,
agencies are subject to routine monitoring when they award contracts
to the private sector. It is even more important that there be an
independent examination of the contract because of a revised estimate
of the cost savings. Originally, the FAA said that outsourcing FSS
functions would save the taxpayers some $2.2 billion over the life of
the contract. Because of some unanticipated transition costs, the FAA
now pegs the savings at $1.7 billion over 10 years.

In February 2005, the FAA awarded an initial five-year contract to
Lockheed Martin with an option for a five-year extension. The company
will be consolidating 58 flight service stations — excluding three in
Alaska — into 20 facilities. The move toward outsourcing was triggered
by escalating costs associated with the old FSS system, the FAA's
inability to effectively modernize the FSS computer system, and
widespread inefficiencies.

Updated: May 18, 2006, 1:03 p.m. EDT


On Wed, 19 Apr 2006 19:14:53 GMT, Larry Dighera
wrote in :

On Mon, 03 Oct 2005 01:56:45 GMT, john smith wrote in
::

Anyone have any experiences with the new provider?



It looks like LocMart is not able to meet it's cost savings estimates
nor its schedule:


-------------------------------------------------------------------
AVwebFlash Volume 12, Number 16a -- April 17, 2006
-------------------------------------------------------------------


MODERNIZATION TAKES TIME
(http://www.avweb.com/eletter/archive...ll.html#192030)
A massive effort to replace communications and data lines that stitch
together the air traffic control system is (surprise, surprise) behind
schedule and not achieving its financial goals, according to the New
York Times
(http://www.nytimes.com/2006/04/09/us...1&oref=slogin).
The contract to replace the system was issued in 2002, awarded to
the Harris Corporation, was supposed to be completed by now, but
the scheduled was extended in December, 2005. Marion C. Blakey,
the administrator of the F.A.A., acknowledged in a recent
interview that it would be "a climb" to stick to the revised
schedule, which calls for completion in December 2007. And the
initial estimate that the new system could save $800 million over
10 years has been revised, with savings now estimated at $600
million over 15 years.

The Times story also says the program has caused three failures that
resulted in flight delays.

The failures have come from a variety of causes. On March 6, the
system lost contact with a radar near Chicago, leading controllers
to hold scores of planes on the ground. The problem was that a new
line had failed and that the old one had been prematurely
disconnected by the F.A.A., the agency acknowledged.

However, Harris Corp., which won the contract to do the conversion,
said in a news release
(http://www.harris.com/view_pressrele...kup&pr_id=1832)
last week that the work is on schedule and will reduce the FAA's
costs. The program, called the FAA Telecommunications Infrastructure,
was awarded to Harris Corp. three years ago, and will replace all the
lines linking 4,400 installations, including remote mountain radio and
radar sites. It's supposed to be done by the end of the year but
likely won't be finished until the end of 2007, according to the Times
story.
http://www.avweb.com/eletter/archive...ll.html#192030